Environmental Risk

ActivitySituationAspectImpactInitial RatingDescriptionActionsResidual RatingSignificantControlled
OfficeNormalAir EmissionsGeneration of CO2. Use of Oil ResourcesLowUse of electricityLowNoNo
Site ActivitiesNormalAir EmissionsGeneration of CO2. Use of Oil ResourcesMediumCO2 emmissions generated by transport to site.Maintain vehicles properly
Minimise Transport
LowNoNo
Site ActivitiesNormalContaminationSoil ErrosionHighSoil erosion resulting from disturbance of waterways.Install silt fences as required to prevent soil erosion MediumYesYes
Site ActivitiesNormalCultural HeritageDisturbance Damage Removal of items of Cultural HeritageMediumDisturbance Damage Removal of items of Cultural HeritagePrior to commencement of works at a site, items of heritage significance will be located and identified in the project specific Environmental Management Plan, so that construction practices may be modified to minimise disturbance to these items (e.g. where sandstone curb and gutter in a street is to be crossed, boring should be the means by which work is completed to minimise the risk of damage).
If any items of relics of Aboringinal or European heritage significance are identified during the project work will cease immediately at that location. Ages Build Project Manager must be notified immediately who will notify the Principal to enable them to contact relevant authorities.
Consultation with traditional owner groups and confirmation of required induction and monitoring is to be undertaken by the Principal.
LowNoNo
Site ActivitiesNormalDischarge of WaterStorm Water Run OffMediumSoil erosion resulting from storm water..Project Environmental Management Plans
Water management in accrodance with Guidelines for Errosion & Sediment Control
LowYesYes
Site ActivitiesNormalDisturbance of Land - ExcavationDustMediumDust created during excavationDust control measuresLowNoNo
Site ActivitiesNormalEnergy EmissionsNoiseMediumNoise from construction activitiesNoise pollution shall be minimised by ensuring that the normal working hours of the contract or project are adhered to whenever possible.

Working hours in accordance with specific conditions as specified by the nominated authorities

No work shall be performed outside these hours unless approvals have been obtained from the client & or the local regulatory authorities. No audible work shall take place between the hours of 7.00am & 8.00am Saturdays.
Local residents are to be advised of pending works in the area by means of a “letter box drop’ advising of possible noise disturbance.
All plant & machinery used shall have the necessary silencing mechanisms filled & be in good working order.
All requirements for the testing or monitoring of noise levels as specified by statutory authorities shall be performed in accordance with the required specifications & regulations
Consideration shall be given during the design Process for placement of equipment where it may cause noise disturbance to the public / residents
LowNoYes
Emergency SituationsAbnormalHazardous MaterialsContaminationMediumPaints & other chemicals.Appropriate storage of paint
Minumum quantities
LowNoNo
Emergency SituationsAbnormalHazardous MaterialsContaminationMediumPaints & other chemicals.Effective Emergency ResponseLowNoYes
Site ActivitiesAbnormalContaminationLandfill, Contaminated Soil, WasteMedium
Landfill, Contaminated Soil, Waste
Document emergency procedures to manage all reasonably foreseeable harm, including spills and other environmental emergencies
Obtain the agreement of the Principal to procedures for handling oil, chemicals and other dangerous goods before placing them on the Site, including secure storage arrangements
Inspect the Site daily to ensure appropriate environmental controls are in place and operating effectively, and that all environmental management requirements are being met
LowNoYes
Site ActivitiesAbnormalDischarge of WaterStorm Water Run OffMedium
Storm Water Run Off
Only water of drinkable quality can be discharged into the drainage system.

Contamination can be pre-existing & found at the site during works or be the result of spillages, inappropriate protective measures, accidents or other abnormal activity.

Contaminated water can be recognised by:

An irregular or unnatural colour is noticed
A pungent smell is noticed
A visibly peculiar texture (chemical slicks, cloudy)
Any indicator of unusual water conditions are noticed
Contaminated land can be recognised by:

In irregular or unnatural colour is noticed
A pungent smell is noticed
A visibly peculiar texture (black tar, powdery texture)
Ant indicator or unusual soil conditions are noticed
LowNoYes
Site ActivitiesNormalHazardous MaterialsContamination - ACM. Disturbance during Site ActivitiesMediumContamination - ACM. Disturbance during Site ActivitiesEffective management of ACM -SubcontractorLowNoYes
WasteNormalWasteContaminated SoilHighContaminated soil from excavation entering waterways.Project specific Environmental Management Plans
Excavation only be undertaken when no heavy rainfall is predicted and footings are then to be poured as soon as possible to minimise the exposure time.
Any excavated material shall be used to fill voids as appropriate.
Stockpile locations of material to be approved by the Principal prior to placement.
Correct methods for the disposal of waste.
MediumYesYes

Aspects Register

Process Map